109/2000 Project name: 14.4 MW Ulan Hot Power Plant Project Investment Model: investment construction installed Capacity: 14.4 MW Gri
-
Project name: Anhui Huainan Yuguang Complementary Power Station Investment Model: Investment and construction installed Capacity: 20MW G
-
Project name: Sichuan Hanyuan Wind Farm Investment Model: Advancing Cooperation installed Capacity: 47.5 MW Date: December 5,2016
-
Project name: Yanyuan Phase III investment Model: Investment and construction installed Capacity: 50MW Grid-connected date: June 30,2016
Total:6 Page:1/2 PrePage:4
1 |